Replacement Strategy for Composite Insulators on Transmission Lines

Maintenance, Utility Practice & Experience

Powerlink Queensland is a government-owned network service provider that builds and operates the extensive transmission network in Queensland, Australia. As of 2019, approximately 30,000 non-ceramic insulators (NCIs) were installed on this system that operates at 110 kV, 132 kV, 275 kV and 330 kV.

This edited past contribution to INMR by Tony Gillespie of Gillespie Power Consultancy and Glenn Stapleton, Principal Transmission Engineer at Powerlink, offered a case history of how Powerlink applied its NCI condition monitoring and replacement prioritization strategy. It also presented key conclusions arising from two decades of experience with composite insulators on its transmission system.


Case Study

Demonstration of application of the assessment framework was undertaken for several as-installed insulator populations in the Powerlink network. This case study demonstrated the assessment process for a sub-population of two products, each one supplied by a different supplier. These products were generically classified and defined as:

• Catalogue Item 1 from Supplier A;
• Catalogue Item 2 from Supplier B.

Table 1 below outlines technical and design details, ratings and the size of the installed population that required a decision on replacement sequence and timing. Note that the insulator population being considered in this case study were only installed in suspension “I” string positions. The strain configuration insulator population was evaluated separately. The Table shows that Catalogue Item 1 was installed on two separate assets, both located in dry inland environments and each energized at different voltages. This allowed sensitivity of voltage stress for assets in similar environmental conditions to be demonstrated. Catalogue Item 2 was installed in a region of greater rainfall for an asset that is located closer but not directly on the seacoast.

Advertisement

Desktop Study Discussion

The insulators in this case study were essentially equivalent in age, i.e. 19 and 20 years in service, with Supplier B being the older. In terms of failure history, there had been no recorded failures for Catalogue Item 2 from Supplier B. One relatively recent failure occurred for Supplier A, but this involved a different catalogue item with shorter creepage and arcing distance versus Catalogue Item 1 from that supplier, as shown in Table 1. The failure occurred in a 275 kV application after the unit had been in service for about 22 years and was attributed to incorrect installation/positioning of the corona ring.

Climate in the area where the failure occurred saw localized higher rainfall and longer duration of wetting. In fact, wetting duration for the recorded failure was well in excess of the assumptions made in Table 1 for Catalogue Item 1 from Supplier A. E-field modelling was performed and maximum electric field stresses on NCIs equipped with grading rings fitted were found to be as follows:

• Catalogue Item 1, 330 kV line voltage, lattice steel structure has a calculated electric field of 0.3 to 0.35 kV/mm on the sheath;

• Catalogue Item 1, 275 kV line voltage and on a tighter phase spaced lattice steel structure has a calculated electric field of 0.10 to 0.30 kV/mm on the sheath;

• Catalogue Item 2, 275 kV line voltage also has a calculated electric field in high stress areas of 0.10 to 0.30 kV/mm on the sheath.

Contamination affecting the insulators from Suppliers A and B were predominately dust generated from the inland location of the line as well as agriculture in some sections. No known pollution flashovers had been recorded for these assets during their circa 20 years of operation. Outages had occurred due to lightning, with ground flash densities in some localized storm asset corridors and regions in the range of 3 to 4 strikes/km2/yr. Recorded lightning outage rates per circuit used in the sensitivity study are summarized in Table 3.

Table 4 summarizes the PIPA generated times to degradation onset and respective degradation modes, by supplier, along with the relative probability of encountering these conditions. The desktop study suggested an additional 5-year window may exist before onset of degradation for Catalogue Item 1 when the unit is operating at lower voltage stresses from 275 kV and in dry inland environments. It also suggested that potentially more degradation modes could become apparent during inspection of Catalogue Item 2 from Supplier B.

Table 1: Design Details & Relative Populations for Insulators in Case Study

Sampling & EHV Laboratory Testing

Visual inspections were undertaken on samples recovered from the field to assess condition, with special focus on the triple seal and also on sheds located in the high E-field zone. Hydrophobicity tests were also conducted. Visual condition and hydrophobicity class comparisons were then made to sample photos available from the EPRI ageing chamber reporting tool. Degradation noted on these recovered samples as well as from photos taken during the latest climbing patrols of random structures were reviewed for signs of onset of advanced degradation. Anticipated degradation conditions of note, on a supplier basis, are highlighted in the Projected Condition(s) column of Table 3.

Advertisement

Degradation had not significantly exceeded conditions evident on artificially-aged units from the same supplier compared using EPRI’s ACRT tool. Performance of Catalogue Item 2 from Supplier B, based on all available inspection data, indicated that in-service condition of these units was better than degradation estimates based on desktop study tools. A sensitivity analysis of key wetting duration and electric field stress parameters would help calibrate actual performance versus revised assumptions for time to degradation.

Visual inspection of Item 1, recovered from 330 kV applications, indicated some weakening of the shed material, but no tearing or erosion was evident in-service. A corona scan from helicopter was also performed for Supplier A insulators, in both 275 and 330 kV service locations, for the population outlined in Table 2.

EHV testing was also performed, as summarized in Table 2. No discernible pattern was noted for Catalogue Items 1 and 2 that would indicate that resistive leakage current worsened when comparing readings taken before and after impulse tests on the complete insulators. Moreover, no discernible pattern was noted when comparing leakage current data on new and old units of the same catalogue item.

In retrospect, the merits of conducting power frequency leakage tests are questionable and this might be due to the reasonably good integrity of the insulators recovered for the purpose of testing. Dry leakage current testing may prove more applicable to units that have undergone advanced deterioration but may be just as apparent as results from simple visual inspection. The merits of future EHV sampling tests using dry leakage current measurements was therefore planned to be reviewed and investigated further on a larger set of recovered insulators that showed more deteriorated condition and were no longer in-service due to age. Extending the power frequency test to include a wet test might also be considered to establish whether this would better quantity the effect of loss of hydrophobicity.

Table 2: Inspection & Test Regime for Sampling & Removal from Service

Steep front impulse testing did not identify or accelerate any degradation mode. This was noted both when testing complete units and testing pre-conditioned cut and boiled units. Still, these tests did provide valuable information on initial concerns for risk of internal voids and poor adherence of sheath to rod. Such failure modes were initially identified in the population assessment tools as applicable with finite probability for certain units of particular vintage and manufacturing/formulation parameters. Performing an e-field scan of the insulator before and after steep front impulse testing also provided a means to determine the extent of any internal deterioration from such testing, which proved of insufficient severity to cause flashover.

Advertisement

Table 3 summarizes typical time to failure estimates. These appear to provide lifetime estimates for some units in excess of 25 years in certain environments. But in reality, the fleet management approach adopted by Powerlink has aimed to balance financial impact, labour resources and focus on minimizing risk of not being able to perform timely replacement as needed. This usually has resulted in actual replacement scheduled earlier than this. Of course, should future replacement be possible without maintaining focus on this being conducted live, there would be scope to extend the replacement cycle past 25 years in the case of some insulator suppliers.

Fig. 1 highlights Powerlink’s existing approach to management and scheduling for live line replacement for Catalogue Items 1 and 2. This is presented in terms of the classifications for NCI wetting performance as well as corrosion region used to classify environment for cap & pin insulators and galvanized hardware supporting insulator strings. Corrosion regions in Queensland are classified from C1 (minimal) to C5 (extreme) risk. It should also be noted that ideal replacement intervals for insulators depends as well on replacement and refurbishment intervals for towers and components. In this regard, insulator replacement needs to align with scheduled intervals for replacing steelwork and other line hardware.

Fig. 1: Service life estimates adopted for Catalogue Items 1 and 2.
Fig. 1: Service life estimates adopted for Catalogue Items 1 and 2.
Table 3: Projected Priority & Replacement Window Expectations by Insulator Supplier & Location

Conclusions

Non-ceramic insulators (NCIs) have been successfully applied on the Powerlink Queensland transmission system. Powerlink has continued to purchase and install composite insulators but with reduced rollout frequency given more restricted deployment criteria. Most existing line assets equipped with large populations of NCIs are scheduled to be re-insulated with the latest generation of this same technology – but mainly where risk of bird chewing damage is seen as low and where the service environment maximizes life expectancy of these replacement units.

Advertisement
PPC Insulators

The key requirement of being able to undertake the majority of replacement work live presents a challenge when using a fleet management approach. Timing replacement must take account of projected insulator condition while also maintaining an acceptable risk profile for live line working as well as compliance associated with risk of dropped conductor. Moreover, finite human resources to undertake replacement work limit the total number of strings that can realistically be changed in any year. The ‘step change’ in NCI penetration into the Powerlink network that peaked in the early 2000s has resulted in large numbers of NCIs together now approaching theoretical projected end-of-life.

Population assessment approaches and tools have aided Powerlink to develop a priority and solid engineering basis for planning and undertaking NCI replacement programs. To support the fleet management approach, desktop models, health indices, end of life assessment and replacement prioritization are all being performed using population assessment tools developed by EPRI. Successful application of this approach was demonstrated with a case study for three sub-populations of NCIs installed on the transmission network and planned and prioritized for replacement.

[inline_ad_block]

INMR LABORATORY GUIDE


More about Mechanical Tests